We were appointed to undertake the development of the proposed new library in the town centre.

The existing library was in a state of disrepair and it was considered that the site would be more valuable if it could be developed in part for housing. The capital receipt for the proposed housing needed to cover the proposed new build costs of the library so that there would be no additional cost to the County Council.

Key Info

Type:
New Build

Value:
£600k

Location:
Eye, Suffolk

Duration:
6 months

Client:
Suffolk County Council – Corporate Services – Corporate Property
End User:
Suffolk Libraries

Contractor:
R G Carter

Disciplines:
Architecture, Building Services Design, Interior Architecture, Landscape Architecture, Quantity Surveying + Cost Consultancy, Structural + Civil Engineering

Imagery

01
02
03
04
05
06
07
08
/
01
02
03
04
05
06
07
08

Scope

Our multi-disciplinary team worked closely to provide a variety of successful solutions which met the client’s requirements.

The sale and acquisition of land was carried out by our Estates team.

We needed to tailor the design to suit the tight programme deadlines and lower the impact on the local community. An offsite manufactured Structural Insulated Panel System (SIPS) was implemented to reduce road closure times which resulted in a faster construction process. Collaboration with Suffolk County County Council, Mid Suffolk District Council and Suffolk Libraries was necessary to deliver a space suitable for a modern library in the town centre. The closure of the car park had to be planned in advance to ensure it was programmed to suit key shopping periods. Library staff were included in key decisions on internal design and layout to make certain the space designed was dedicated to their use.

A high level of recyclable materials were integrated into the design (for example aluminium windows and timber cladding). These materials reduced the impact on the environment and lowered costs.

Testimonial

“It’s been a great team effort with Suffolk County Council, Concertus and RG Carter working together with Suffolk Libraries to deliver a modern library facility that will provide a better library environment and experience for everyone in the local community.”

James Powell, Suffolk Libraries

Result

The project was delivered within budget and by the client’s ambitious deadline.

The library has been very well received by the local community, Suffolk County Council and Suffolk Libraries.